| TEMPORARY SUSPENDED SCAFFOLD AS PER DRAWINGS. SUSPENDED SCAFFOLD SHALL COMPLY WITH CH 33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRES | 64 ESSEX STREET, Manhattan |
Other | Oct 23, 2026 | 4 | $5 to $25 million |
| Modify existing Sprinkler system. No Change in use, egress or occupancy. | 157 WEST 57 STREET, Manhattan |
Other | Oct 23, 2026 | 8 | $1 to $5 million |
| INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND CONSTRUCTION PLYWOOD FENCE AS PER PLANS. TEMPORARY EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF T | 675 THIRD AVENUE, Manhattan |
Other | Oct 23, 2026 | 5 | $1 to $5 million |
| installation of construction fence to protect site, during full demolition | 19-12 BROOKHAVEN AVENUE, Queens |
Demolition | Oct 23, 2026 | 2 | Under $250,000 |
| installation of construction fence to protect site during full demolition | 19-08 BROOKHAVEN AVENUE, Queens |
Demolition | Oct 23, 2026 | 2 | Under $250,000 |
| installation of construction fence to protect site during full demolition | 19-14 BROOKHAVEN AVENUE, Queens |
Demolition | Oct 23, 2026 | 2 | Under $250,000 |
| installation of construction fence to protect site during full demolition | 19-10 BROOKHAVEN AVENUE, Queens |
Demolition | Oct 23, 2026 | 2 | Under $250,000 |
| PERFORM INTERIOR PARTITION, HUNG CEILING DEMOLITION & CONSTRUCTION IN CONJUNCTION WITH APARTMENT RENOVATION #6A. REPLACE EXISTING PTAC UNITS | 975 PARK AVENUE, Manhattan |
Demolition | Oct 23, 2026 | 5 | $250,000 to $1 million |
| Install of temp tents, platforms and prod equip., no alt to exist structures for IC Annual Work Permit. TPAs filed as required. Producer is | 68 33 STREET, Brooklyn |
Other | Oct 23, 2026 | 3 | Under $250,000 |
| MODIFICATIONS OR SPRINKLER SYSTEM AS PER PLANS. | 54-08 74 STREET, Queens |
Other | Oct 23, 2026 | 2 | Under $250,000 |
| INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLDS PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2022 BUILDING CODE CHAPTER 33. NO CHANGE IN USE, EG | 8 CARLISLE STREET, Manhattan |
Other | Oct 23, 2026 | 3 | Under $250,000 |
| DIRECT REPLACEMENT OF (4) ROOFTOP HVAC UNITS | 501 SEAVIEW AVENUE, Staten Island |
Mechanical | Oct 23, 2026 | 6 | $250,000 to $1 million |
| Installation of new partitions, doors, ceilings and finishes on the 41st and 42nd floors (Woodline- Marketing Floors 43 & 44) as per plans. | 712 FIFTH AVENUE, Manhattan |
Roofing and exterior | Oct 23, 2026 | 10 | $1 to $5 million |
| S01362856-I1 | 27 ABINGDON AVENUE, Staten Island |
Other | Oct 23, 2026 | 3 | Under $250,000 |
| INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAP | 250 MERCER STREET, Manhattan |
Other | Oct 23, 2026 | 4 | Under $250,000 |
| FILING HEREWITH CIVIL SITE WORK WITH TEMPORARY RESTRIPING AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION. FILED | 41 SEAVER WAY, Queens |
Other | Oct 23, 2026 | 10 | $5 to $25 million |
| NON-ILLUMINATED NON-ADVERTISING DOUBLE-SIDED PROJECTING ACCESSORY SIGN FOR NYC HEALTH - DELIVERIES NYC HEALTH. NO CHANGE OF USE, EGRESS OR O | 40 WEST 137 STREET, Manhattan |
Major renovation | Oct 23, 2026 | 2 | Under $250,000 |
| INTERIOR RENOVATION #510 WORK IN 1ST FL OF EXISTING 6 STORY BUILDING. DEMOLITION WORK AND CONSTRUCTION WORK AS PER PLAN. INSTALL HVAC, PARTI | 504 GRAND STREET, Manhattan |
Demolition | Oct 23, 2026 | 8 | $1 to $5 million |
| Facade repair. No change in use, occupancy, or egress. | 4 DARTMOUTH STREET, Queens |
Roofing and exterior | Oct 23, 2026 | 2 | Under $250,000 |
| INTERIOR RENOVATION OF THE 18th FLOOR OFFICE SPACE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. | 14 WALL STREET, Manhattan |
Major renovation | Oct 23, 2026 | 4 | Under $250,000 |
| SUSPENDED SCAFFOLD OUTRIGGER SYSTEM FOR EXTERIOR FACADE RESTORATION WORK AT 75 BAXTER STREET, MANHATTAN, NY 10013 | 75 BAXTER STREET, Manhattan |
Roofing and exterior | Oct 23, 2026 | 2 | Under $250,000 |
| Installation of new lowered concrete slab floor and additional support for existing portions as required. | 247 WEST BROADWAY, Manhattan |
Major renovation | Oct 23, 2026 | 5 | $250,000 to $1 million |
| NON-STRUCTURAL DEMOLITION AND RENOVATION OF APT 4MN. GENERAL CONSTRUCTION OF PARTITIONS, DOORS AND REPLACE PLUMBING FIXTURES WITH EXISTING R | 45 SUTTON PLACE SOUTH, Manhattan |
Demolition | Oct 23, 2026 | 12 | $1 to $5 million |
| STRUCTURAL MODIFICATIONS REQUIRED TO PROVIDE A NEW FLOOR OPENING IN THE EXISTING 1ST FLOORFRAMING. STRUCTURAL MODIFICATIONS REQUIRED FOR RE- | 71-14 AUSTIN STREET, Queens |
Roofing and exterior | Oct 23, 2026 | 2 | Under $250,000 |
| FILING FOR INTERIOR DEMO OF 35TH THROUGH 39TH FLOORS AS PER PLANS SUBMITTED HEREWITH. | 345 PARK AVENUE, Manhattan |
Demolition | Oct 23, 2026 | 28 | $5 to $25 million |
| FILED HEREIN VERITICAL AND HORIZONTAL EXTENSION ON EXISTING 3 STORY + CELLAR BUILDING (MIXED USE, STORE + 2 DWELLINGS); PROPOSED CONVERSION | 102 MESEROLE STREET, Brooklyn |
Major renovation | Oct 23, 2026 | 4 | $1 to $5 million |
| INTERIOR RENOVATION OF APARTMENT 35C. PARTITION CHANGES TONON-LOAD-BEARING WALLS AS PER PLANS. NO CHANGE IN USE,OCCUPANCY OR EGRESS. | 310 GREENWICH STREET, Manhattan |
Major renovation | Oct 23, 2026 | 9 | Under $250,000 |
| Interior renovation for apt 14CD, work includes removal & installation of non-bearing partitions, new bathroom layouts & laundry room &new k | 525 PARK AVENUE, Manhattan |
Roofing and exterior | Oct 23, 2026 | 8 | $250,000 to $1 million |
| THIS APPLICATION IS FILED FOR FOUNDATION INCONJUNCTION WITH Q01157851-I1 | 31-60 31 STREET, Queens |
Other | Oct 23, 2026 | 2 | $250,000 to $1 million |
| FILED HEREWITH; 8' CONSTRUCTION FENCE. THIS APPLICATION SHALL APPLY TO DEMO AND NEW BUILDING 86 & 88 ARDMORE AVENUE LOTS: 18, 19 | 88 ARDMORE AVENUE, Staten Island |
Demolition | Oct 22, 2026 | 1 | Under $250,000 |